Green Frame Renovation: Price and What Remains to Be Done

A green frame apartment renovation with works and materials costs about 300-650 GEL per m² at the economy level. Mid-range finishes cost 500-1,100 GEL per m², while premium starts at 800 GEL and above.

In a green frame apartment, you still need to finish:

Level
300-650GEL per m²
500-1,100GEL per m²
800+GEL per m²
Floor area (m²)
Your estimate30,000 to 66,000 ₾

Renovating a 60 m² green frame apartment at this level costs about 30,000-66,000 GEL (2026).

Labour and materials. Not included: furniture, appliances, debris removal (about 150-300 GEL a truckload) and cleaning after the works (about 15 GEL per m²). Keep about 10-15% of the budget aside for the unexpected; we start any extra work only after your written yes.

What is and isn't in the price
Request our estimate
  • Bathroom
  • Wall preparation and painting
  • Flooring and interior doors
  • Lighting, and often the heating boiler and radiators

Tbilisi has three apartment handover states: black frame (bare shell), white frame (plastered shell), and green frame. A green frame is the most complete state, but the flat is not ready to move into.

The developer usually leaves these works completed:

  • Plastered walls and a floor screed
  • Electrical wiring
  • Installed water, sewage, and heating pipes

Inclusions vary by developer, so always ask the developer for a detailed written list of included works. You can compare all frame types side by side on Frame Types.

How much does a green frame renovation cost per m²?

With works and materials included, a green frame renovation costs 300-1,100 GEL per m². Premium materials push the green frame renovation price higher.

Green frame renovation price per m², 2026
Level Price
Economy 300 to 650 GEL per m²
Mid-range 500 to 1,100 GEL per m²
Premium 800 GEL and above per m²

How much does it cost to renovate a 40, 50, or 60 m² green frame apartment?

Renovating a 50 m² green frame apartment costs 15,000-32,500 GEL at the economy level. A mid-range renovation for a 50 m² flat costs 25,000-55,000 GEL, and a premium renovation starts from 40,000 GEL.

In US dollars, the 50 m² economy renovation costs about $5,800 to $12,500. The conversion uses the National Bank of Georgia rate of 2.5973 GEL per US dollar (3 November 2026).

Estimated total by floor area and level
Floor areaEconomyMid-rangePremium
40 m² 12,000-26,000 GEL 20,000-44,000 GEL from 32,000 GEL
50 m² 15,000-32,500 GEL 25,000-55,000 GEL from 40,000 GEL
60 m² 18,000-39,000 GEL 30,000-66,000 GEL from 48,000 GEL

To calculate any other floor area, use the calculator at the top of the page.

What work remains in a green frame apartment?

In a green frame apartment, you still need to complete the final surfaces, fixtures, furniture, and appliances:

  • Bathroom fit-out
  • Final wall preparation (primer and paint or wallpaper)
  • Flooring and interior doors
  • Lighting with switches and sockets
  • Heating boiler and radiators, plus furniture and appliances

Final switches and sockets are usually not fitted, and most flats have no toilet, sink, or shower installed.

Radiators are fitted only in some cases, while the boiler is often left to the buyer’s choice.

Bathroom: what remains and what it costs

Remaining bathroom work covers waterproofing, wall tiles and floor tiles, a toilet, a sink, and a shower system.

Even in a green frame, the bathroom is sometimes left without plastering or a floor screed.

The tiler must set the floor slopes for the drain position and tile size. Always ask the developer if the bathroom is plastered and screeded.

The main parts of the bathroom budget are:

  • Tiler’s labour (work only, no materials): about 800-2,000 GEL for a standard bathroom
  • Wall tiles and floor tiles: about 25-120 GEL per m²
  • Sanitaryware set: about 1,500-4,000 GEL

Water and sewage pipes are usually already laid, leaving only fixture connections.

Running the pipe and connecting the fixture costs 80-110 GEL per point in labour. That rate applies if the bathroom was left unfinished or you add a new wet point (plumbing point).

Costs rise with tile size, 45-degree mitred corners, concealed systems, a glass shower cabin, and the sanitaryware brand.

Walls: painting or wallpaper

In a green frame, walls are usually plastered and leveled, ready to paint. Only primer and paint, or wallpaper, remain on the walls.

Painting and decorating labour costs 5-25 GEL per m² of wall surface. Total wall area is about 2.5 to 3 times the floor area because you finish exterior walls and both sides of partitions.

Flooring

Flooring remains to be installed, which means laminate with underlay and skirting boards. Laminate material costs about 20-60 GEL per m², and laying labour costs 5-25 GEL per m².

Heating, lighting, and electrical points

Heating pipes are usually laid, but the boiler and radiators often still need to be bought and fitted. Radiator installation labour costs about 100 GEL per radiator.

Lighting also remains, including chandeliers, light fixtures, switches, and sockets. Extra electrical points, such as for an air conditioner, raise the cost at 15-40 GEL per point for installation labour.

Doors

Interior doors remain to be fitted, although some developers already include them in a green frame. One interior door costs about 250-800 GEL.

How much does labour cost for each job?

The table shows unit prices for labour (work only, no materials) so you can check the labour items in an estimate. Material prices are listed in the sections above.

Labour price per unit (without materials)
WorkLabour per unit
Additional electrical point (running cable to the point, fitting a socket or switch) 15 to 40 GEL per point
Painting and decorating 5 to 25 GEL per m² of wall
Laying wall tiles and floor tiles (tiles up to 60 cm) 20 to 80 GEL per m²
Laying laminate 5 to 25 GEL per m²

What increases the cost of a green frame renovation?

Material quality makes the biggest difference in the total renovation price.

  • Material quality. Wall tiles, floor tiles, flooring, and doors.
  • Bathroom fit-out. Tile size, 45-degree cuts, concealed systems, a glass shower cabin, sanitaryware brand, and the number of bathrooms.
  • Heating system. The boiler and radiators, when the developer has not installed them.
  • Lighting and electrical points. Additional points increase the price.
  • Ceiling solution. Stretch ceilings, Barrisol, multi-level plasterboard (drywall) ceilings, and recessed lights.

Green, white, or black frame: what is the difference for renovation?

A green frame leaves the least work and the simplest renovation, but the apartment purchase price is the highest. A black frame is the opposite, and a white frame sits in between.

Bringing a standard 50-150 m² flat from black frame to green frame costs about 190-250 GEL per m² without building partitions.

The price covers works and materials, or about 11,000-15,000 GEL for a 60 m² flat, including:

  • Wiring and plastering
  • Heating and water pipes
  • Floor screed

Compare the developer’s price difference between a black frame and a green frame for the same apartment. Buying a green frame therefore pays off when that difference is less than that amount.

Green, white, and black frame compared for renovation
GreenWhiteBlack
What remains to be done Final finishes, bathroom, doors, lighting, and often boiler and radiators Also electrical wiring, heating pipes, and plumbing pipes Everything, including plastering and floor screed

A white frame leaves more work (wiring, pipes to each point, heating); see full prices on White Frame Renovation.

A black frame requires every stage; see the full list and prices on Renovation from a Black Frame.

Frequently asked questions

How long does a green frame renovation take? For an apartment up to 60 m², a green frame renovation takes about 30-45 days, depending on the scope of remaining work.

How much should I keep in reserve? Keep about 10-15 percent of your budget in reserve for unexpected costs.

Are the sockets and switches left by the developer enough? Final sockets and switches are usually not installed in a green frame. Installing an additional electrical point costs 15-40 GEL per point in labour.

Is furniture included in these prices? Always ask for furniture to be shown as a separate item in any estimate, as a separate budget covers:

  • Furniture and built-in furniture
  • The kitchen
  • Appliances

Can I get an estimate from abroad? Yes, you can write in English.

How we run a job for owners abroad is on renovation for owners abroad.

How to get a preliminary estimate for your apartment?

To get a preliminary estimate, send your apartment’s floor area, building type, and green frame condition. Include your planned works and photos of each room.

Request an estimate

Based on your floor area, building type, and photos, you get a free reply by email, WhatsApp, or Viber within 2 working days, with no obligation. Before the contract we see the flat, in person or on a video call, and fix the price.

Our schedule is booked until January 2027, so new renovations start from January. You still get your estimate now, and we agree the date to see the flat now.