Black Frame Renovation: Cost, Works, and Timeline
Renovating a black frame (bare shell) apartment in Tbilisi costs 300-600 GEL per 1 m² for economy. Mid-range costs 400-900 GEL per 1 m², and premium costs 700-1,500 GEL or more.
A black frame renovation usually takes 2 to 3 months. A large black frame apartment takes up to 4 months.
All-in black frame prices cover works and materials, without furniture or appliances.
For a 60 m² flat, an economy renovation costs 18,000-36,000 GEL. At the National Bank of Georgia rate of 2.5973 GEL per US dollar (3 November 2026), that is about $6,900 to $13,900.
A premium renovation for 60 m² is 42,000-90,000 GEL or more.
Calculate an estimated range for your floor area and finish level.
LevelA black frame renovation for 60 m² at this level costs about 24,000 to 54,000 GEL (2026).
Labour and materials. Not included: furniture, appliances, debris removal (about 150-300 GEL a truckload) and cleaning after the works (about 15 GEL per m²). Keep about 10-15% of the budget aside for the unexpected; we start any extra work only after your written yes.
What is and isn't in the priceA black frame has no internal wiring, plumbing, or heating, and interior partition walls are partly or completely missing. Your renovation therefore covers every stage:
- Partitions
- Wiring
- Plastering
- Floor screed
- Wet points (plumbing points)
- Finishing
Read what a black frame means to see how it differs from a white frame (plastered shell). The guide also covers a green frame (pre-wired shell ready for finishing).
How much does a black frame renovation cost per 1 m²?
A black frame renovation per 1 m², including works and materials, costs 300-600 GEL for economy. Mid-range costs 400-900 GEL per 1 m², and premium costs 700-1,500 GEL or more.
| What the price includes | Price |
|---|---|
| Economy level: works and materials, with basic materials | 300 to 600 GEL per 1 m² |
| Mid-range level: works and materials, with mid-grade materials | 400 to 900 GEL per 1 m² |
| Premium level: works and high-end materials | 700 to 1,500 GEL and above per 1 m² |
| Premium package with a design project: design, materials, and works, without furniture or appliances | 1,500 to 2,500 GEL per 1 m² |
What makes the price per 1 m² higher or lower?
The price per 1 m² depends on whether a quote covers labour (work only, no materials) or works and materials. The price per 1 m² also depends on the material grade and a design project.
A premium package with a design project reaches 1,500-2,500 GEL per 1 m². Before comparing two per-m² quotes, check whether materials are included and what grade they are.
How much does a 50, 60, 80, and 100 m² apartment cost from a black frame?
Renovating a 60 m² apartment from a black frame costs 18,000-36,000 GEL for economy. Mid-range for 60 m² costs 24,000-54,000 GEL, and premium costs 42,000-90,000 GEL or more.
The table below multiplies each floor area by the per-m² tiers above.
| Area | Economy | Mid-range | Premium |
|---|---|---|---|
| 50 m² | 15,000-30,000 GEL | 20,000-45,000 GEL | 35,000-75,000 GEL and above |
| 60 m² | 18,000-36,000 GEL | 24,000-54,000 GEL | 42,000-90,000 GEL and above |
| 80 m² | 24,000-48,000 GEL | 32,000-72,000 GEL | 56,000-120,000 GEL and above |
| 100 m² | 30,000-60,000 GEL | 40,000-90,000 GEL | 70,000-150,000 GEL and above |
A premium package with a design project costs 1,500-2,500 GEL per 1 m². For a 60 m² apartment, that package comes to 90,000-150,000 GEL.
Why does a small apartment cost more per square metre?
A small flat costs more per m² because wet points (plumbing points) take up a larger share of the floor plan. Complex utility hubs also take up a larger share of a 40 to 50 m² floor plan:
- Material delivery, tradesperson call-outs, and debris removal take the same effort for 40 m² as for 100 m².
- A small apartment still needs the same heating hub with a boiler, manifold, and cabinet as a large one.
At the same finish level, a smaller flat therefore usually costs more per 1 m² than a larger flat.
What works are included in a black frame renovation?
A black frame renovation goes through every step from building partitions to final cleaning, as covered in our renovation stages guide.
The jobs below are listed in the exact order they happen on site.
- Partitions. Internal walls are built first using blocks or plasterboard (drywall).
- Electrical wiring. Cables are installed before the walls are plastered.
- Plastering. Walls are plastered and left to dry thoroughly before the next stage begins.
- Floor screed. Floor screed is poured only after plastering and never before, because mortar droppings during plastering damage a finished screed.
- Skim coat, filler (putty). Walls and ceilings are smoothed and prepared.
- Wall tiles, floor tiles, and wet points. Wall and floor tiling is completed in the bathroom and wet areas.
- Paint, flooring, and doors. Painting and decorating, floor laying, and interior door installation are completed.
- Plumbing fixtures, lighting, and cleaning. The sink, toilet, bath or shower, and light fixtures are fitted, the flat is cleaned, and construction debris is removed.
The table below lists unit prices for labour (work only, no materials) so you can check each line of an estimate.
| Work | Labour price |
|---|---|
| Laying a block partition wall | about 25 GEL per 1 m² of partition |
| Plasterboard (drywall) partition, single layer | about 20 to 40 GEL per 1 m² |
| Electrical point (wiring to the point, socket or switch installation) | 15 to 40 GEL per 1 point |
| Wet point (plumbing point: pipe to the point and fixture connection) | 80 to 110 GEL per 1 point |
| Heating pipe point (about 1 point per 10 m²) | 50 to 80 GEL per 1 point |
| Radiator installation | about 100 GEL per 1 radiator |
| Underfloor heating | 30 to 70 GEL per 1 m² |
| Wall plastering | 15 to 25 GEL per 1 m² |
| Floor screed | 10 to 20 GEL per 1 m² |
| Skim coat, filler (putty) | 5 to 30 GEL per 1 m² |
| Painting and decorating | 5 to 25 GEL per 1 m² |
| Wall tiles and floor tiles (tiles up to 60 cm) | 20 to 80 GEL per 1 m² |
| Laying laminate | 5 to 25 GEL per 1 m² |
| Air conditioner installation | about 250 GEL per 1 unit |
What must you decide before plastering and floor screed?
Before plastering and floor screed, you must decide on everything hidden inside the walls and under the floor before they are closed up.
Wiring goes in before plastering, while plumbing and heating pipes go in before the floor screed.
A design project serves as a technical plan with exact drawings for wiring, plumbing, heating, air conditioning, furniture, and lighting.
What to decide before plastering and floor screed
- Partitions. Partitions in a black frame are often partly or fully missing. Fix the layout of your living room, bedrooms, and other zones right away, as walls are built first.
- Heating. Choose between radiators and underfloor heating before the floor screed is poured. Heating pipes are laid before the screed, and underfloor heating raises the floor level.
- Wet points (plumbing points). Plan waterproofing, floor slopes, and bathroom drains before the tiler starts work.
- Sockets. Set the spots for your bed, TV, desk, kitchen appliances, and lighting before walls are chased. Sockets then sit at the right place and height.
- Air conditioning. Prepare air conditioner pipes and lines during the rough-in stage while the walls are still open.
How long does a black frame renovation take?
A black frame renovation usually takes 2 to 3 months. A large black frame apartment takes up to 4 months.
How much do you save with a green frame?
With a green frame, you save about 190 to 250 GEL per 1 m² of flat on rough-in works and materials. Rough-in works between black and green frame also take about 15 to 35 days:
- Electrical wiring
- Plastering
- Heating and water pipes
- Floor screed
Buying a green frame pays off when the developer charges less than that amount per 1 m² as a premium. This figure assumes the black frame already has partitions built.
Where partitions are missing, add the partition cost from the FAQ below to that threshold.
By comparison, a green frame renovation involves fewer stages and therefore takes less time.
Frequently asked questions
Are materials included in the black frame renovation price?
The per-m² tiers on this page cover works and materials, excluding furniture and appliances.
Market quotes vary: some cover labour only, while others include partial materials. Always ask crews to break down each quote into labour and materials.
How much does it cost to build partition walls?
As a rough guide, total partition area in a flat is close to its floor area:
- A single-layer plasterboard (drywall) partition costs about 20-40 GEL per 1 m² for labour.
- Laying a block partition costs about 25 GEL per 1 m² of partition for labour. With blocks and adhesive, it costs about 40-45 GEL per 1 m².
- Carrying blocks up into the flat adds about 400-1,000 GEL per apartment.
How much does heating cost in a black frame?
Underfloor heating raises the floor level, so choose it before the floor screed:
- Heating pipe labour costs 50-80 GEL per 1 point, calculated at about 1 point per 10 m².
- Radiator installation is about 100 GEL per 1 radiator.
- Underfloor heating is 30-70 GEL per 1 m².
How much does a design project cost?
Interior design services can cost 25-130 GEL per 1 m².
In a black frame, a design project fixes the exact positions of sockets, pipes, and heating before the walls and floors are closed up.
Can I get an estimate from abroad? You can write in English for a free written preliminary estimate, with no obligation:
- It comes within 2 working days by email, or by WhatsApp or Viber to your number.
Request an estimate
Based on your floor area, building type, and photos, you get a free reply by email, WhatsApp, or Viber within 2 working days, with no obligation. Before the contract we see the flat, in person or on a video call, and fix the price.
Our schedule is booked until January 2027, so new renovations start from January. You still get your estimate now, and we agree the date to see the flat now.