Renovation Estimate: What to Include and a Sample
A renovation estimate is an itemised document that lists every job and material on its own line. Each line states the unit, quantity, unit price, and line total.
A complete estimate also sets out what is excluded from the price, the payment schedule, and the work timeline. Below is a sample estimate for a 60 m² apartment at our 2026 prices.
What Should an Estimate Include?
Your estimate must state the apartment’s floor area, condition, and a list of materials. Each task needs a separate line with its unit, quantity, and unit price.
The estimate should also list works excluded from the price and a stage-by-stage payment schedule. The quote must also state the duration of the job and the date until which the prices remain valid.
A properly structured estimate is grouped by renovation stages: demolition, rough works, mechanical and electrical works, finishing, and cleaning.
Materials are separated into their own group so you can see the cost of each stage clearly.
- Property Address, floor area in m², and existing condition of the apartment. State the developer shell type, such as black frame or white frame, or an old renovation.
- Work item Each task is listed on its own line rather than combining several processes under one name.
- Unit The unit used to measure the work (m², linear metre, point, piece, or set).
- Quantity The number of units measured for your apartment.
- Unit price The price of a single unit and the line total (quantity multiplied by unit price).
- Materials Each material with its quantity and price, or a clear note that you are buying the materials yourself.
- Exclusions Works and costs not covered by the price (for example rubbish removal, materials, kitchen, or furniture).
- Payment A payment schedule where each instalment is tied to a completed stage.
- Timeline How long the work will take and the date until which the quoted prices are valid.
Sample Estimate: 60 m² Apartment
The sample estimate below shows what a stage-by-stage estimate looks like for a 60 m² apartment. The unit prices are our 2026 price ranges.
The quantities are illustrative and do not describe your specific flat.
What is included in the calculation?
The calculation assumes:
- About 160 m² of wall area and 55 m² of floor and ceiling
- One electrical point per square metre (60 points) and 6 wet points (plumbing points)
- 5 radiators
- 30 m² of tiles (about 10 m² of bathroom floor tiles and about 20 m² of wall tiles)
- 45 m² of laminate
- About 10% cutting waste for tiles and laminate
| Work or material | Unit | Quantity | Unit price, GEL | Total, GEL |
|---|---|---|---|---|
| Demolition | ||||
| Strip-out of old tiles with bagging of debris | m² | 15 | 5-25 | 75-375 |
| Construction rubbish removal | load | 2 | about 150-300 | about 300-600 |
| Rough works | ||||
| Hand plastering of walls | m² | 160 | 15-25 | 2,400-4,000 |
| Floor screed | m² | 55 | 10-20 | 550-1,100 |
| Wall skim coat (filler) | m² | 140 | 5-30 | 700-4,200 |
| Mechanical & electrical | ||||
| Electrical point installation | point | 60 | 15-40 | 900-2,400 |
| Wet point (plumbing point), with pipe runs and fixture connection | point | 6 | 80-110 | 480-660 |
| Radiator installation | piece | 5 | about 100 | about 500 |
| Finishing | ||||
| Wall tiles | m² | 30 | 20-80 | 600-2,400 |
| Laminate laying | m² | 45 | 5-25 | 225-1,125 |
| Painting of untiled walls and ceiling | m² | 195 | 5-25 | 975-4,875 |
| Materials | ||||
| Ceramic tiles | m² | 33 | about 25-120 | about 825-3,960 |
| Laminate | m² | 50 | about 20-60 | about 1,000-3,000 |
| Bathroom sanitaryware set | set | 1 | about 1,500-4,000 | about 1,500-4,000 |
| Interior door | piece | 4 | about 250-800 | about 1,000-3,200 |
| Cleaning | ||||
| Post-renovation cleaning | m² | 60 | about 15 | about 900 |
| Sample line items total | 12,500-37,500 | |||
| Contingency reserve, 10-15% | 1,200-5,600 | |||
| Total including reserve | 13,500-43,500 | |||
Dollar Equivalent and Exclusions
The sample total including the reserve equals about $5,200 to $16,700. (43,500 / 2.5973 = 16,748, which rounds to $16,700.) The conversion uses the National Bank of Georgia rate of 2.5973 GEL per US dollar (3 November 2026).
The sample estimate does not include:
- Rough materials (plaster and screed mix, tile adhesive, filler, paint)
- Cables and pipes
- The kitchen
- Furniture and appliances
- Windows
How to Use This Sample
Replace the quantities in the sample table with the figures for your apartment and multiply each quantity by the unit price.
The detailed estimate attached to our contract uses the same lines as this sample, so you can check that every job is there.
How to Read a Crew’s Estimate
Check the crew’s estimate against the list above and compare every line before signing a works contract. The warning signs below show what you should ask the crew about before agreeing.
Seven Signs an Estimate Is Incomplete
Our price per m² for each type of renovation is on apartment renovation prices.
Estimate, Calculator, and Price per m²: What Is the Difference?
| Tool | What it gives you | Accuracy | When to use it |
|---|---|---|---|
| Price per m² | Price range per square metre of the flat | Roughest guide, shows our overall price range | For an initial sense of cost before you start |
| Calculator | Range based on your floor area and frame type | Closer to your apartment, but still a range | While planning your budget |
| Preliminary estimate | Written assessment based on your area, building, frame condition, work list, and photos | Close to your apartment, with quantities estimated from the details you send | Before we see the flat and fix the price |
| Detailed estimate | Every task and material listed separately, with quantities measured on site | Most accurate | Before signing a works contract |
Try the renovation calculator first to get an approximate ballpark figure.
Free Preliminary Estimate at Proremonti
At Proremonti, the preliminary estimate is free, while a detailed estimate requires measuring quantities on site. We prepare the preliminary estimate from the details you send:
- Floor area and building type
- Frame condition
- Work list and photos
If you are managing your renovation from abroad, you can write in English for a free written preliminary estimate. See renovation for owners abroad.
We reply within 2 working days by email, or by WhatsApp or Viber to the number you give. The preliminary estimate carries no obligation. Before the contract we see the flat, in person or on a video call, and fix the price.
How Much Does It Cost to Prepare an Estimate?
On the Tbilisi market, preparing an estimate with a site visit and measurements often carries a fee. For a 60 m² apartment, the estimate preparation costs about 170-350 GEL.
Several companies deduct the estimate fee from the cost of the work if you hire them for the renovation.
Frequently Asked Questions
How much contingency reserve do I need for unexpected costs?
People usually set aside 10-15% of the renovation budget for unexpected costs. In a properly prepared estimate, the contingency reserve is shown on its own separate line.
Can the estimate change during the renovation?
Yes, an estimate can change if the scope of work or the choice of materials changes.
Every such change should be agreed in writing with a revised version of the estimate showing how the overall total changes.
What format is an estimate sent in?
A renovation estimate is usually sent as a PDF or Excel file. Both file formats let you easily check every line item and total.
Does the apartment have to be measured on site before an estimate is made?
Measuring the apartment on site is essential for a detailed estimate. A preliminary estimate, however, can be prepared from your floor area and the photos you send.
Prices and Calculation
Request an estimate
Based on your floor area, building type, and photos, you get a free reply by email, WhatsApp, or Viber within 2 working days, with no obligation. Before the contract we see the flat, in person or on a video call, and fix the price.
Our schedule is booked until January 2027, so new renovations start from January. You still get your estimate now, and we agree the date to see the flat now.